Work plan
Deadlines
- 2018-02-26 Choose a project proposal and send your choice via email to epsatisep@gmail.com
- 2018-03-05 Define the Tasks (what must be done - every member should preferably participate in every task), subtask allocation (who does what) and Gantt chart (when) of the project and insert them on the wiki (planning)
- 2018-03-12 Upload the “black box” System Diagrams & Structural Drafts to the wiki
- 2018-03-23 Upload the detailed System Schematics & Structural Drawings to the wiki and do the cardboard scale model of the structure
- 2018-04-04 Upload the List of Materials (what & quantity) to the wiki
- 2018-04-14 Upload the Interim Report and Presentation to the wiki. The report must contain the Introduction, including the tasks, team members allocation and Gantt chart, State of the Art, Marketing Plan, Project Management, Eco-eficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography chapters
- 2018-04-19 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks
- 2018-04-23 Complete the List of Materials (local providers & price, including VAT and transportation) to the wiki
- 2018-05-02 Upload refined Interim Report (based on Teacher & Supervisor Feedbacks)
- 2018-06-04 Upload the results of the Functional Tests to the wiki
- 2018-06-15 Upload the Final Report
- 2018-06-18 Upload the Presentation, Video, Paper, Poster and Manual
- 2018-06-21 Final Presentation, Individual Discussion and Assessment
- 2018-06-28:
- Update the wiki with all correction suggestions
- Hand in to the EPS coordinator:
- a CD with the corrected deliverables (source + PDF) together with all code and drawings produced
- a printed copy of the corrected report and poster
- 2018-06-28:
- Hand in the prototype and user manual to the client
- Receive the EPS@ISEP certificate
- Bring typical food from your country
Tasks
Table 1 displays the responsible for each task.
| Project proposal | |
|---|---|
| Initial Planning | |
| Market Research | Maarten |
| Technical Research | Wouter |
| Gantt Chart | Damien |
| Task Allocation | Damien and Maarten |
| Budget Calculations | Mostafa |
| Project Leading | |
| Project Management | Wouter |
| Eco-Efficiency and Sustainability | Maarten |
| Ethical and Deontological Concerns | Maarten |
| Project Definition | |
| Sketches | Wouter |
| Functionalities | Damien |
| Target's Audience | Maarten |
| Construction | |
| Hardware | |
| List of Materials | Wouter |
| Sensors | Damien |
| Body | Maria |
| Software | |
| Arduino Code | Mostafa |
| Testing | |
| Unit Testing | Mostafa |
| Product Testing | Maria |
| Corrections | Mostafa |
| Final | |
| Paper | Mostafa |
| Poster | Maria |
| Video | Maria |
| Leaflet | Damien |
| Evaluation | Wouter |
| Report | Damien |
| Presentation | Maarten |
| Demonstration | Maria |
Gantt Chart
gantt_chart.pdf gantt_chart_2.pdf
Thanks to following zip file, you can find our Gantt Chart.
Updated weekly Gantt chart:
For the first three weeks: gaantchart3.pdf
Updated weekly Gantt chart:
For the first four weeks:
Updated weekly Gantt chart:
For the first five weeks:
For the first six weeks:
The team has inserted the materials that they will use and its price in Microsoft Project. Following file inserted below:
For the first seven weeks:
From the beginning to the Interim Presentation:
The team has updated list of the materials that they will use and its price in Microsoft Project. Following file inserted below:
1st week after the Interim presentation
2nd week after the Interim presentation
3rd week after the Interim presentation
4th week after the Interim presentation
5th week after the Interim presentation
6th week after the Interim presentation
7th week after the Interim presentation
8th week after the Interim presentation
1st week after the final presentation
Final Gaant Chart